Tee Renovations Moved up Two Weeks
Published April 12, 2006
Originally scheduled for a May 1st start, the tee renovations have been rescheduled to commence on Monday April 17th. Due to the mild weather, we decided to take advantage and get an early start.
The Contractor is now moving in his equipment in preparation for an early start on Monday. The first in line are the tees on #18. The project will then proceed to #16 and #3 tees and moving on from there.
In line for renovations and re-leveling are the following tees; #6 intermediate, #18 tees, #16, #15, #13 intermediate and forward tee, #7 tees, #8, #10 tees, #11 tees as well as the forward tee on #9.
We will be using a portion of the parking lot as a staging area. This area will be clearly marked. During busy times, the over flow lot will be available for parking.
During the course of this project there will be times when we will have to utilize temporary tees. We will be making an effort to lesson the disruption to play as much as possible and we will do everything possible to have the new tees back in play as early as possibly feasible. Your patience and understanding is greatly appreciated in this regard. Remember, this is a short-term inconvenience for a long-term improvement.