Moving Along
Published May 10, 2006

The tee renovations are moving along quite nicely. With only three holes left to finish and sod we are way ahead of schedule. Shown in the photo above, the tees on #18 have already been mowed and are knitting in very well. In a week or so we should be ready to open #18 along with #10 tees with others to follow shortly after.

Keeping pace, the finish crew is hard at work trying to bring the tees on #3 and #16 to a close before the forecasted rain due in tonight and over the next few days. Keep up the good work guys.